The Director of Public Works shall, within ten (10) working days of a request therefor, make such inspections as are required and as he deems necessary to insure that all construction is in accordance with the approved plans and specifications. Unless waived in writing by the Director of Public Works, inspections would normally consist of, but are not limited to, the following:

(a) An inspection after completion of the clearing operation.

(b) Inspection during the construction of all earthwork operations.

(c) An inspection of the subgrade prior to the placing of the aggregate base.

(d) An inspection of the aggregate base prior to the placing of the roadway surfacing.

(e) An inspection of concrete forms and reinforcing prior to the placing of any concrete therein.

(f) An inspection of the placing of any concrete or roadway surfacing.

(g) Utilities placement.

(h) Drainage facilities.

(i) A final inspection upon completion of all improvements within the subdivision. (Ord. 1146, § 71, 7/19/1977; Ord. 1290, § 6, 12/12/1978)